Key data

Comprehensive offers in the areas of sports, health, education and events make WIN4 a broad-based centre for the entire population.

Comprehensive offers in the areas of sports, health, education and events make WIN4 a broad-based centre for the entire population.

180623_103_WIN4_deuring22.jpg
180623_103_WIN4_deuring22.jpg

Key Data

  • Sports and health business park on a plot of approx. 26'000m2
  • Financed by the private sector
  • A centre for sport, health, education and sports
  • Sports arena with room for up to 2000 people
  • Indoor facilities for competitive and popular sports
  • Home of the top clubs Pfadi Winterhtur and HC Rychenberg
  • 1st National Floorball Performance Centre
  • Meeting place for sport, economy, politics, culture and society
33964966_1885459388173329_8532237732217356288_o2.jpg
33964966_1885459388173329_8532237732217356288_o2.jpg

Optimal Location

  • Sporty neighbourhood thanks to Deutweg Sports Park with the Zielbau Arena
  • Good accessibility by public transport and car
  • Bus stops directly next to the house
  • Many bicycle and moped parking spaces
  • Paid parking garage available
  • 20 Minutes from Zurich Airport
  • 25 minutes from Zurich
  • 40 Minutes from St. Gallen
180623_156_WIN4_deuring2.jpg
180623_156_WIN4_deuring2.jpg

Sustainability

  • Buildings built to the MINERGIE(-P) standard
  • Power production with photovoltaic system (100 KWpeak) for own consumption community
  • Use of modern SIMXIN fittings to reduce water consumption
  • Sustainable waste concept

 

180623_109_WIN4_deuring22.jpg
180623_109_WIN4_deuring22.jpg

Facts and Figures

  • investment volume. CHF 36 million (1st stage)
  • Client: WIN4 AG
  • Architecture: EM2N Architekten AG
  • Rental space 1st stage 5000m2
  • Rental space 2nd stage 7000m2
  • Total area: 26'000m2
180623_140_WIN4_deuring-Bearbeitet32.jpg
180623_140_WIN4_deuring-Bearbeitet32.jpg

Timeline

  • 25 August 2016 Groundbreaking ceremony
  • 15 March 2017 Foundation stone laid
  • February 2018 Start of construction of the multifunctional training hall
  • End of June 2018 Start of operations AXA ARENA
  • Tenants moving into the campus from August 2018
  • October 2018 Commissioning of the training hall
991_EM2N_winterthur_AUSSEN_B_bearbeitet_indievisual-AG2.jpg

Timeline Stage 3

  • Build of the Sporttrackt 3 named "Kubus"
  • 14 September 2021 groundbreaking ceremony
  • Opening August 2023
  • 6000m2 rental space
  • Main user Academia school